|
Risk Assessment for Closure of Acid
Generating Tailings Areas
Introduction For this
study, detailed characterization of the tailings areas was available from
conventional ABA studies, various kinetic tests and historical data on acid
generating tailings from other regional mines and monitoring data for the
basin. The data showed that the tailings had minimal neutralization potential
(NP), an acid potential (AP) of >100kg/t and minimal lag time between
tailings exposure and the onset of oxidation. Closure strategies that were
considered included various dry covers, elevated water tables, collection and
treatment, and flooding. Conventional environmental pathways techniques were
applied to assess the options and concluded that flooding was the preferred
option at the three sites considered. The weakness in the conventional
assessment was that it considered only routine operations and assumed the
facility would perform as designed. This left both the public and regulators to
ask what were the risks of failure over the long term, were these risks
acceptable, and what were the long-term cost implications of failure and
long-term maintenance of the sites?
In order to address these issues a
risk assessment approach was taken. The risk assessment studies addressed a
variety of factors including: failure modes and consequences from non-routine
events and design/construction flaws; environmental effects that could occur as
a result of failure; the frequency of failure; costs to clean-up and repair the
site in the event of a failure; costs to care and maintain the site in
perpetuity; potential consequences of failure and the need for design change;
and the consequences of failure to maintain the site.
The primary risks
to the facility were the failure of a retention structure which could spill
acid tailings into the environment, and drought which could cause the surface
to dewater and tailings to generate acid and dust. The basic framework for the
model was the @RISK code (commercially available). The model involves a
probabilistic framework that allows for inputs to be entered as distribution
functions (e.g. lognormal, triangular, uniform). The model included four
subroutines, the Maintenance model, Earthquake Response model, Flood Response
model, and Drought model. The subroutines used actuarial statistics on
earthquake frequency, meteorological data, dam failure frequency etc. for
periods of 10,000 years. Where data were not available, expert opinion was used
to fill in these gaps. The consequences of failure were established for each
structure based upon type of failure, depth of breach, volume of water spilled
etc. The outputs of these subroutines fed into the Integration model which was
run for various time periods (200 and 1000 years in this case). The integration
model was used to:
- Predict the number and severity of
occurrences (failures);
- Predict the consequences (tons of tailings
lost, months and areas of beach exposure);
- Determines the cost to repair the site and
remediate downstream damage for each event;
- Calculate total and discounted costs for
maintenance and site repair; and
- Provide summary statistics on the
cumulative probability distributions for cost and failure consequences.
The worst case outputs were also subjected to
detailed environmental assessment to address the potential impacts to human
health and biota (health risk and eco-risk). Figure 1 illustrates the
conceptual approach to the risk assessment from the problem formulation stage
through a feedback loop which triggers consideration of modifications to the
system in the event that some perceived identified attribute of risk fails to
meet the previously established criteria. Figure 2 illustrates conceptually the
integration of the facility risk model described above and the environmental
consequence model used to assess the environmental and health consequences
arising from the accidental release of tailings water and/or solids. A modified
version of the Monte Carlo Assessment tool (UTAP) was used to assess the
potential effects on future water quality, the environment and people. In the
event that failure consequences were deemed unacceptable, the design of the
facility was modified to reduce either the frequency or magnitude of
failure.
Results The probabilistic risk assessment was
an extremely useful tool as it was able to provide key data on the long-term
performance of the flooded basins containing reactive tailings which will
require flooding in perpetuity. The model confirmed:
- Care and maintenance was essential to
reduce the failure rate and consequence. Costs for care and maintenance were
modest with a net present value in the range of $2 million for each of the
three sites assessed.
- Some failures were more likely to occur and
may result in unacceptable consequences. These results were used to modify
designs.
- It was not necessary to implement all
measures to reduce risk as it was demonstrated that the costs for many of these
measures far exceeded benefits.
- The model results provided both regulators
and the public with a level of comfort as the risks for all "what if" scenarios
were quantified (both what can happen and what are the consequences).
- The model was the key tool used to assess
long term costs and financial assurance needs.
Environmental Risks Associated with
Historic Uses of Slag
Some 50 million tonnes have been used
productively as road base, rail ballast or fill for other construction
purposes. Continuing to use slag for construction fill would effectively
increase the longevity of the slag dump.
The objective of this study
was to develop a preliminary generic assessment of the environmental risks
associated with historic uses of slag. The primary purpose was to understand
the potential human health and environmental risks (liabilities) that might
arise from use of slag as construction fill, particularly as might result from
acid generation and metal mobilization. A secondary objective was to provide
input with respect to management of future slag production. The risk assessment
was performed following generally accepted practice. In brief, the major
elements of the human health risk assessment were as follows.
An initial
problem formulation/hazard assessment phased was used for identification and
characterization of slag constituents. An initial screening on the basis of
environmental mobility, toxicity and regulatory limits was performed to
identify the species that were to be considered in the screening risk
assessment. An extensive database was reviewed on the characteristics of slag,
including chemical compositions, mineralogy, chemical reactivity (in terms of
potential acid generation) and leachability. Ranges of characteristics for
slag, and leachate from slag, were developed from the data and used as input to
the risk assessment.
The next phase of the project focused on exposure
assessment using environmental models to assess how the selected slag
constituents move through the environment and result in exposure to people. The
assessment considered potential exposures based on actual past usage of slag as
construction fill, and available studies regarding the environmental
implications of slag storage, and usage in construction applications. These
studies were reviewed, and where appropriate, were used to examine, or provide
a context for, the assumptions used in the risk assessment. Data were available
on surface water, groundwater, soil, vegetation and sediment in the vicinity of
sites where slag was used as construction fill.
Next a dose-response
assessment, or toxicity assessment, using published consensus scientific
literature was carried out to develop toxicity profiles for the various slag
constituents. Lastly a risk characterization was carried out that integrated
the results of the exposure and dose response assessments to describe the
nature and (estimated) magnitudes of potential risks to people.
For
situations where slag is used as construction fill, slag leachate may add to
background levels in nearby streams. In this project, potential ecological
risks to fish and other aquatic species were calculated using a similar
approach to that used for the human health risk assessment.
Sources of
uncertainty exist at each stage of the risk assessment. For the purposes of the
screening risk assessment, intentionally conservative assumptions were made to
ensure that the risks calculated to people or to the environment arising from
use of slag as construction fill are very likely to be overestimated (i.e.
conservative). Some of the uncertainties arise from variabilities in the
leachability of slag, in the calculation of environmental concentrations in air
or water; from the assessment of toxicity or from the characteristics assigned
to the receptors (exposed individuals) themselves.
Based on the
conservative screening calculations described in the report, no human health
effects arising from use of slag as aggregate would be expected. The results of
the risk assessment were input to the company's decision making and strategic
planning process. The work provided guidance for dealing with these materials
during the short term (operational) period, as well as providing the company a
degree of confidence with respect to the long term behaviour of the material
and any potential liabilities that might be associated with the re-use of the
materials.
A Corporate Liability Risk Analysis of Tailings
Decommissioning
The assessment of the potential financial liability
associated with the decommissioning of the Atlas uranium tailings pile, located
on the edge of the Colorado River, provides a classic illustration of the need
to consider potential changes in risk acceptance, linked in this case with
changing demographics, over time in the decision making process. This case
illustrates the dramatic effects that may arise as a result of evolving
legislation, changing social and demographic conditions and the variable nature
of acceptable risk.
In this particular instance, the owner had in place
an approved reclamation plan for its 10.5 million ton tailings stack based on
on-site reclamation in accordance with regulatory requirements. A technical
update (slope stability) in the regulatory guidance required minor revision and
amendment in this aspect of the approved plan. On issuance of the notice of
amendment acceptance by the regulator, public and political opponents of
on-site plan used the comment period to raise new issues. These opponents
successfully solicited enough political support to have the regulator take the
unprecedented step of initiating a new EIS of the previously approved closure
plan and an off-site alternative.
During this period, Atlas was
assessing restructuring options including various merger options. In both
cases, but particularly the latter, a key management decision element centered
on the viability of the existing closure plan, that is, is it appropriately
protective, and what is the likelihood that it would ultimately be found
acceptable or would the off-site option be mandated. To address these
questions, Atlas initiated and carried out a comprehensive corporate risk
assessment program (see Figure 3) that considered the following factors in the
assessment of the potential environmental liability associated with the
site:
- Political issues;
- Local state and federal regulations;
- Regional and local concerns;
- Publicly perceived risks;
- Actual risks;
- Environmental impact potential;
- Engineering considerations and cost;
- Financial options; and
- Fatal flaws
The risk assessment work was carried out in an
interactive manner by a multidisciplinary team that included owner
representatives, national and regional legal counsel, public relations,
engineering, environmental and risk managers. The work included analysis of
existing and alternative reclamation scenarios; review of existing and
uncertain engineering issues, designs, and concepts; assessment of industry
practices and precedents; review of health and safety records; evaluation of
the existing cost basis; assessment of potential health risks to workers and
the public under varying scenarios; and consideration of legal, regulatory and
political drivers that might affect the outcome of the decision-making process.
A detailed probabilistic (Monte Carlo) model was developed that explicitly
included the uncertainties associated with the decommissioning concepts, the
engineering requirements and outstanding engineering issues, long-term
performance considerations including various failure modes, and consequence
scenarios.
The risk assessment supported the validity of the original
plan. It illustrated that while the health risks associated with either option
were small, the health risk for the off-site option were six times higher than
those of the on-site option, while the costs of the off-site option were about
ten times that of the on-site option. The corporate risk assessment also found
that the area of most uncertainty with respect to the selection of a final plan
lay in the political arena.
|